Much work has been done on the Caterpillar facility. Precast walls are currently being erected onsite. Roof girders are being installed as the building progresses with portions of the roof being fitted on a daily basis. It won’t be long until the main manufacturing facility is dried in. Work continues on site with ponds receiving final grading and permanent vegetation.
Clearing has been completed on the access roads and rough grading is in progress. Staging for the storm sewer system installation is forthcoming while culvert crossings are currently being installed.